RPN
Severity
Occurrence
Detection

RPN interpretation thresholds

RPN rangePriorityAction required
≥ 200CRITICALMandatory action — redesign or process change. Cannot ship product.
120 – 200HIGHAction required — develop containment plan and timeline before next phase.
60 – 120MEDIUMPlan corrective action — address in next continuous improvement cycle.
< 60LOWMonitor only — no immediate action required.
Severity = 9 or 10SAFETY/REGAction mandatory regardless of RPN — design out the failure mode.

What is FMEA RPN?

FMEA (Failure Mode and Effects Analysis) systematically identifies potential failures in a product or process, ranks them by risk, and drives corrective action. RPN (Risk Priority Number) is the numerical risk score:

RPN = Severity × Occurrence × Detection

Each factor is rated 1-10 per the AIAG-VDA FMEA Handbook (2019), so RPN ranges from 1 to 1000.

The Three Factors Explained

RPN Worked Example

A bolted joint on a transmission housing.

Corrective action: Add Loctite or torque-angle method, plus in-process torque verification. New ratings:

AIAG-VDA Action Priority (AP) Method

The 2019 AIAG-VDA handbook moved away from RPN-only to Action Priority (H/M/L) based on combinations of S, O, D — not just the multiplied number. Severity 9-10 is always High Priority regardless of O and D, because safety / regulatory effects can never be left unaddressed.

RPN Interpretation Thresholds

Common FMEA Mistakes

Related Tools

FMEA feeds directly into PPAP Element 6. Use Cp/Cpk studies to validate that your corrective action actually reduced occurrence. For inspection planning, use AQL sampling to set sample sizes proportional to risk. For cost justification, see Cost of Poor Quality.